Contract Award - January 29, 2014, the project was awarded to OHL USA, Inc. for $74,841,795 Construction - March 2014 - April 2017
PROJECT UPDATENovember 2015: Construction continues on schedule. Overall construction is approximately 63% complete. The installation of the oxygenation system will be finished by early December. The Project 77 diversion structure and the Maintenance Yard work are making steady progress. The work on the box culvert at Figueroa Drain and the invasive plant removal in the Wetlands North area are almost complete.