City Sewers Current Construction
Odor Control – Rodeo Road and La Cienega Boulevard
Project construction is taking place in the intersection of Rodeo Road and La Cienega Boulevard. The work includes maintenance hole and related improvements that will reduce odors in this area and make these sewers more reliable for decades to come.
QUICK FACTS
- Five maintenance holes will be replaced with new pressure rings and covers. Two trap maintenance holes will be upgraded. A 72”, 35-foot long bypass channel will be bulk-headed and slurry filled. There are currently two 4' by 8' existing sluice gate access covers that will be replaced.
- Construction period: spring 2010 through late 2011. Weather or other circumstances could shift the work schedule. Neighbors will be informed as conditions warrant.
- Construction will generally take place Monday through Friday, from 7:00 a.m. until 4:00 p.m., and on major streets from 9:00 a.m. until 3:30 p.m. to minimize traffic impacts.
- Estimated Cost: $320,000.
- Trucks and other equipment such as pipes will be used during construction, and you may see open trench excavation and debris removal.
- Dust control will be provided in all project areas.
- Enclosures or other barriers will be used in construction areas wherever necessary for public safety.
- Flaggers will be used where traffic is impacted. Traffic will be restored to normal when construction has been completed at the end of each workday.
- Trash pickup, deliveries, access to businesses and residential driveways will be maintained.
- Parking may be temporarily restricted in some areas, and signs will be posted in advance telling you where and when.
- You will be notified 24-48 hours in advance whenever sewer services may be temporarily interrupted.
|